Online monitoring system for foundation pit
1. Monitoring Background
Urban foundation pit excavation has the characteristics of high construction risk and difficulty. At present, the excavation of foundation pits in Shenzhen, Guangzhou, Dongguan and other places is getting deeper and deeper, from the initial four to eight meters to the current maximum depth of more than twenty meters. Due to the complexity of underground soil properties, load conditions, and construction environment, determining design and construction plans solely based on geological survey data and indoor geotechnical test parameters often contains many uncertain factors. Monitoring changes in soil properties, environment, adjacent buildings, and underground facilities caused during the construction process has become an essential part of engineering construction, as well as guiding the eyes for correct construction and a necessary measure to avoid accidents. It is also an information technology. Currently, foundation pit monitoring and engineering design and construction are listed as the three basic elements for ensuring the quality of deep foundation pit engineering.
II. System Overview
Integrating structural health monitoring with IoT architecture, cloud computing, local area network/communication network, and other multi network seamless connection technologies, an intelligent online monitoring system for foundation pits is established to provide real-time monitoring for the construction site. The monitoring system based on cloud computing service center can accommodate monitoring data of tens of thousands of structures such as bridges, tunnels, slopes, etc., forming a regional structural health monitoring platform to achieve unified monitoring and management of all structures within the region.

III. Main Monitoring Contents
1. Building foundation pit: top settlement and horizontal displacement of retaining piles (walls), deep horizontal displacement of retaining piles (walls), internal forces of retaining piles (walls), deep horizontal displacement of soil outside the pit, anchor rod axial force, groundwater level, support axial force, and bottom uplift
2. Surrounding risk sources: surface subsidence, pipeline subsidence, building inclination, uneven settlement of buildings, building cracks, bridge pier inclination, uneven settlement of bridge piers
IV. Monitoring Diagram

V. List of Monitoring Projects
| Monitoring item | Device name |
| Supporting axial force | Strain gauges, axial force gauges |
| Anchor rod axial force | Reinforcement meter |
| Groundwater level | Pore water pressure gauge |
| Vertical displacement of column structure | Fully automatic robot |
| Support pile (wall), vertical and horizontal displacement at the top of the slope | Fully automatic robot |
| Horizontal displacement of support pile (wall) body | Series fixed inclinometer |
| Surface subsidence | Static level, total station robot |
| Vertical displacement of underground pipelines | Fully automatic robot |
| Vertical displacement of buildings (structures) | Static level |
| Cracks in buildings (structures) | Crack gauge |
| Vertical displacement of bridge piers and abutments | Fully automatic robot |
| Bridge pier column inclination | Box type fixed inclinometer |
| Bridge cracks | Crack gauge |
VI. Monitoring Basis
Technical Specification for Construction Monitoring of Urban Rail Transit Engineering DG/TJ 08-2224-2017Technical Specification for Monitoring of Urban Rail Transit Engineering GB50911-2013Technical Code for Monitoring of Building Foundation Pit Engineering GB50497-2009Technical Standard for Monitoring of Building Excavation Engineering GB 50497-2019
7. Implement Functions
1. 24-hour real-time monitoring: By real-time online monitoring of supporting structures, surface settlement, and inclination of retaining piles, the structural changes of building foundation pits can be grasped in real time.
2. Report push: Real time display and release of monitoring results, and regularly push monitoring reports to users.
3. Multi level warning: Establish a three-level alarm mechanism, and when abnormal data is detected, send SMS or text messages as soon as possibleNotify users in real, broadcast and other forms to achieve comprehensive warning function.
4. Emergency plan handling: Extract corresponding handling methods directly from the expert system, take timely measures such as personnel intervention and road blockade, and eliminate safety hazards in their infancy.
5. Structural trend analysis: Through monitoring data analysis and safety evaluation during the construction period of the foundation pit, structural stability trend analysis can be achieved.
6. Historical data storage: The storage of monitoring data provides an analogy basis for the design and construction of similar projects in the future.