Project Background
The Jinsha River Bridge of Yibin Chengdu Guiyang Railway is a key control project of the Leshan Guiyang section of the Chengdu Guiyang Railway. The total length of the bridge is 1874.90 meters, and it has set four bridge construction records after completion: the setting of railway bridge deck on top and highway bridge deck on bottom is the world's first dual-use bridge for both public and railway; The main span is 336 meters, making it the world's largest span steel box arch bridge; The height difference between the highway bridge deck and the railway bridge deck is 32 meters, ranking first in the world; The first domestically developed dual-purpose steel box arch bridge system in China combines the rigid and flexible suspension rods of highway bridge decks with the rigid suspension rods of railway bridge decks.
Bridge appearance diagram
                                                                       
Project Design and Implementation
Feishang Technology has adopted a self-developed magnetic flux system for monitoring the force on the tie bars of the Jinsha River Bridge on the Yibin Chenggui Railway. A total of 64 magnetic flux sensors are used throughout the bridge to monitor the force on the tie bars in real-time, ensuring the safety of bridge operation at all times.
Schematic diagram of tie rod elevation layout
 
Magnetic flux is measured through non-contact methods, avoiding the problem of sensor fatigue and truly achieving non-destructive monitoring of bridge tie rods. At the same time, cable force monitoring can be established without affecting bridge operation, achieving long-term effectiveness of cable force monitoring.
Construction period: Guide the cable tension value during the construction process to ensure that the tension value meets the design requirements;    
Operation period: Monitor the trend of cable force changes during bridge operation, and provide maintenance decision-making reference for management and maintenance units.
Magnetic flux construction installation diagram
Bridge construction period diagram
Magnetic flux construction installation diagram