Monitoring Background
TJ3105 marker building of Ningbo Rail Transit Line 3 Phase I Project is located at the north side of Tongtu Road, running south-north along Zhongxing Road. The station crosses Jiangjiahe River. The station is a reinforced concrete box structure with two floors of single column and double span underground. The first underground level is the station hall level, and the second underground level is the station platform level. The central mileage of the station is YDK17+434.000, and the width of the station foundation pit is 44.6m, with a length of approximately 153.60m. The depth of the south and north end head well foundation pits is 19.514m and 19.207m, respectively; The depth of the standard section foundation pit is about 17.76m. The foundation pit is constructed using the open cut method, and the enclosure type is an 800/1000mm thick underground continuous wall.

Plan of Soul Tower Station
Main monitoring content
| MonitoringContent | Monitoring device |
| Steel support axial force | Three chord axial force meter |
| Temperature and humidity of foundation pit | Temperature and humidity sensor |
For the monitoring of steel support axial force, FS-ZL30A three string axial force meter is used. Based on the classical string principle, the three steel strings of the three string axial force meter are evenly distributed around the pressure bearing surface of the axial force meter. It can effectively avoid inaccurate monitoring data caused by eccentric compression. In addition, temperature and humidity monitoring of the foundation pit has been added. < br />
Cloud Platform Applications

Home GIS positioning

Real time continuous trend chart of monitoring points

Axial force trend chart
Data association

Alarm Management
Expert review
On March 28, 2017, Ningbo Rail Transit Group Co.,Ltd. organized an expert review meeting for the scientific research project "Research on Automated Monitoring and Application of Steel Support Axial Force and Pit Bottom Uplift" undertaken by our company. The meeting invited many industry experts, including Shanghai Tunnel Institute, Beijing Urban Construction Institute, China Railway First Institute, China Railway Group, Wuhan University of Technology, and East China Jiaotong University, to participate in the review.
< br />Expert review meeting
At the review meeting, the experts carefully listened to the construction report of the project team, had lively exchanges and discussions on the research and application of subway automation monitoring technology, and fully affirmed our technology and platform application. They unanimously agreed that the research results of this project have significant social and economic benefits, have promotion value and application prospects, and have reached the advanced level in China as a whole. They agree to pass the review.

Report Management