首页 > Jinjiang Foundation Pit
Jinjiang Foundation Pit
Jinjiang Foundation Pit

Jinjiang Foundation Pit

I. ProjectBackground

The starting point on the north side of the Jinjiang Eastern Expressway project is about 781m north of Fuxing Road, and the endpoint on the south side is about 488m south of the Weitou branch line. The starting and ending station numbers are K3+140~K8+937, with a total length of about 5.797km. The second section of the Jinjiang Eastern Expressway Phase I project (K7+055~K8+937) is 1.882km long. The scope of this section includes highway engineering (including overall, route, roadbed, pavement, tunnel, route intersection, traffic safety facilities, tunnel attachments, green landscape, other projects, highway related projects, etc.), facilities along the line (including municipal drainage, power pipelines, etc.), and project costs.

The starting mileage of the main tunnel is located at K7+125 and the ending mileage is K8+825, with a total length of 1700m. Among them, K7+125~K7+165 is a single-sided retaining wall section, K7+165~K7+280 is a north open section, K7+280~K8+500 is a tunnel buried section, and K8+500~K8+825 is a south open section. The main line tunnel is designed as first-class highway and urban expressway, with a design speed of 80km/h, and the ramp tunnel is designed as urban trunk road, with a design speed of 40km/h.

Figure 1-1 Site photo of foundation pit

Figure 1-2 Site photo of foundation pit

II. Project Design and Implementation

During the construction of the foundation pit, the excavated soil mainly includes plain fill (1-1), miscellaneous fill (1-3), slope silty clay (5-22), residual sandy cohesive soil layer (6-22, 6-23), locally fully weathered granite (7-10), and sandy strongly weathered granite (7-11) layer; Among them, 1-1 plain fill and 1-3 mixed fill are both soft soils with characteristics such as easy softening and collapse when exposed to water; Residual sandy cohesive soil (6-22), residual sandy cohesive soil (6-23), 7-10 fully weathered granite (7-10), and sandy strongly weathered granite (7-11) layers are all special rock and soil with adverse characteristics of easy softening and disintegration when soaked in water.

This project adopts two monitoring methods: manual and automated.

Manual monitoring: Monitor the slope section of the Jinjiang East Expressway, and manual monitoring mainly includes slope horizontal and vertical displacement, as well as groundwater level monitoring.

Automated monitoring: deep horizontal displacement of pile body, horizontal and vertical displacement of pile top, axial force of steel support, internal force of reinforced concrete support, settlement of support columns, groundwater level outside the foundation pit, settlement of surrounding (pit top) surface, and settlement of surrounding buildings.

Table 2.1 Monitoring Content and Measurement Point Layout

Monitoring project

Serial number

Location of measurement points arrangement

Principles for Layout of Measurement Points

Number of measuring points (pieces)

1

Deep horizontal displacement

Internal part of pile (wall)

Distance of 40m

48

2

Horizontal and vertical displacement of pile top

Upper end of drilled pile

Distance of 40m

48

3

Steel support axial force

Supporting end

Take a monitoring section for every 5 reinforced concrete supports, with one axial force meter for each steel support on each monitoring section

48

4

Internal force of reinforced concrete support

Reinforced concrete support inside

Take a monitoring section every 5 reinforced concrete supports, with two monitoring points for each reinforced concrete support

96

5

Support column settlement

Column end

Not less than 2% of the total number of columns and not less than 3 columns

48

6

Pit top water level and vertical displacement

Surrounding the foundation pit

Distance of 40m

48

7

Groundwater level monitoring

Groundwater level outside the foundation pit

Hole spacing 40m

48

8

Settlement of surrounding buildings

Corner points and column foundations of buildings

Monitor buildings within 1-3 times the excavation depth of the foundation pit

4

Figure 2-1 Overall layout of measuring points

III. Function Implementation

Data Statistics

Figure 3-1 Cumulative displacement trend chart of K7680-CXY04 pipe group (left X, right Y)

 

Figure 3-2 Trend chart of axial force of reinforced concrete support


Copyright © 2026 All Rights Reserved 版权所有· 江西飞尚科技有限公司      备案号:赣ICP备13000994号-1     许可证编号:赣B2-20230512
技术支持:
专属客服
专属微信客服