Surrounding Buildings Of Qingdao Metro Line 6
Surrounding Buildings Of Qingdao Metro Line 6

1. ProjectBackground

The first phase of Qingdao Metro Line 6 has a total of 21 stations, including Xintun Road Station, Chaoyangshan CBD Station, Huashan 1st Road Station, Chuangzhi Valley Station, Shishan Road Station, Huanghai College Station, Haigang Road Station, Chaoyang Road Station, Emeishan Road Station (which has been implemented synchronously with Line 1), Fuchunjiang Road Station, Qiantangjiang Road Station, Binhai College Station, Qingyi West Hospital Station, Gangtou Station, Huanghe Road Station, Huaihe West Road Station, Keluoshi Station, Zhamashan Station, Heluobu Station, Sino German Industrial Park Station, and Ecological Park Station.

The first phase of Qingdao Metro Line 6 has a total length of 30.476 kilometers and complex geological conditions. It has repeatedly crossed unfavorable geological conditions such as soft upper and hard lower water rich strata, high-strength intrusive rock veins, and weathered deep troughs; The rock mass has rich development of joints and fissures, high activity, and extremely high requirements for safety construction control indicators, resulting in high construction risks.

II. Project Design and Implementation

According to the geological conditions of the Phase I project of Line 6, the characteristics of station support structures, the bidding documents, and the requirements of the owner, Chaoyang Road Station, Fuchunjiang Road Station, Huanghe Road Station, Gangtou Station, and buildings along the entire line (within the impact range of blasting vibration velocity) are selected as third-party automated monitoring objects for this project.

The specific projects of automated monitoring are as follows:

Monitoring of deep horizontal displacement of pile body;

Concrete support axial force monitoring, steel support axial force monitoring;

Monitoring of blasting vibration velocity of surrounding buildings;

Serial number

Monitoring project

Monitoring object

Monitoring equipment

1

Monitoring of deep horizontal displacement of pile body

Retaining pile

Series fixed inclinometer

2

Concrete support axial force monitoring

Concrete support

Steel bar meter

3

Steel support axial force monitoring

Steel support

Axial force meter

4

Monitoring of blasting vibration velocity of surrounding buildings

Surrounding buildings

Magneto electric speed sensor

 

Project flowchart

  • Project Difficulties

Taking Fuchunjiang Road Station as an example, the geology belongs to the river floodplain landform, and the terrain is generally flat. The thickness of the Quaternary system is about 8.9-13.0m, and the covering layer is the Quaternary Holocene filling soil layer, the Holocene flood alluvial coarse gravel sand, the organic medium sand, the organic powdery clay, the powdery clay, the silty clay, the medium sand, and the gravel sand layer. The underlying bedrock is tuff, and the small mileage section locally intrudes into granite porphyry rock. The groundwater volume is moderate.

  • Solution:

The construction process of Fuchunjiang Road Station includes retaining pile construction, crown beam construction, concrete support construction, segmented excavation of earthwork and installation of steel supports and anchor cables, followed by pouring of the bottom plate and sequential completion of the upper structure construction. Earthwork excavation adopts the form of segmented excavation.

  • Warning Grading

The warning is divided into three levels: yellow, orange, and red.

Report yellow and orange warning messages to the monitoring management center within one day for daily monitoring work.

When a red alert is detected in daily monitoring work, it should be immediately reported to the monitoring management center in an effective and efficient manner to strengthen technical communication and joint warning analysis. The report information should be reissued through the information platform or written form within 2 hours.

ThreeImplement Functions

The subway engineering system is huge, densely populated, enclosed, and has high safety risks. Once an unexpected accident occurs, the resulting casualties and economic property losses will be difficult to estimate. Feishang Technology combines automated monitoring with manual monitoring. In the past, traditional subway construction mainly relied on manual monitoring for foundation pit and tunnel monitoring, resulting in slow information transmission efficiency; Dangerous and complex conditions in the construction site environmentThe traditional manual monitoring method has limited frequency and cannot grasp the construction status in real time. However, the automated monitoring system adopted this time achieves real-time dynamic monitoring, remote remote visualization, and other functions, greatly improving the efficiency of data collection, transmission, and processing in the safety risk monitoring process, reducing personnel safety risks, and enabling full coverage and no blind spots in the monitoring range.

 

 